Mr Le Kim Thanh, General Director of Project Management Unit Rail (MOT) said, far overhead railway projects Cat Linh - Ha Dong has completed 90% of construction value.
The signatories committed to complete the project on schedule elevated railways
So far, the project has completed 13.05 km main rail and road routes to try the train. Own train 13 also has completed production and is completing procedures to import about Vietnam. ...
Mr. Nguyen Hong Truong, Deputy Minister of Communications, said that the high rail project on Cat Linh - Ha Dong has completed 90% despite volume, but 10% of the workload of procurement, equipment installation is very large, need determination from all concerned units.
Deputy require general contractors to meet financing for construction subcontractors to ensure timely commissioning vessels at elevated rail project to March 11/2017. Therefore, he requested the Chinese EPC contractor to perform the work items proposed schedule. In particular, to take the initiative in the first year of construction, not to slow progress, it is necessary to conclude the remaining subcontractors package.
At the same time, finishing the work early procurement of equipment to carry out the first installation of equipment from April to ensure the quality of technology and completed as designed ...
Deputy request: "Project Management Committee railways, EPC contractor and subcontractor units should make every effort to May 11/2017 put the project into test mining. May 2/2018 to officially put into commercial exploitation ".
For elevated rail projects Cat Linh - Ha Dong completed on schedule, put into operation from the date of 10.01.2017, the Board of Management of railway projects have a specific building plans to complete each item.
Accordingly, before the date of 03.31.2017, the project will complete the entire construction architectural decoration (including station Depot).
15/3 days, begin installation of equipment and completion date of 07/31/2017. Date 07/31/2017, energized the entire route.
Uptime uninterrupted train a minimum of 3 months and up to 6 months, depending on the test results before the committee over the project put into operation from 30.09.2017.